RESULTS OF FULFILLMENT OF INVESTMENT OBLIGATIONS FOR ALMATY POWER PLANTS JSC FOR 2021

CHPP-2 named after A. Zhakutov

In 2021, the following activities are being implemented at CHPP-2 in accordance with the Investment Budget:

Reconstruction of combined ash and slag removal system at CHPP-2 (stage 6). Performing of Construction and installation works.

To improve the reliability of power supply to consumers, by ensuring the continuity of the production of electrical and thermal energy, a set of measures is being carried out on the territory of CHPP-2 for the facility "Reconstruction of the combined ash and slag removal system of CHPP-2 (stage 6) of JSC "AlES".

Technological solutions provide for the implementation of construction and installation works for the development, transportation and storage of ash and slag waste.

Implementation of design solutions of the 6th technological stage will allow storing ash and slag in section No. 1 of ash dump No. 1 (with a capacity of 3,812.3 thousand m3) for 2.54 years, with a design output of ash and slag of 1,500 thousand m3 per year.

Ash dump before construction work

After completing the CMP

"Repair/modernization of elevators/elevator shafts (Replacement of a freight elevator with a capacity of 3.2 tons)" for the department of CHPP-2 named after A. Zhakutov of JSC "AlES"

Decommissioning of the PG-359 type freight elevator type PG-359, reg. No. L 15-135, reason - Order No. 35-E dated 10/27/2020, issued by the KSU "Housing Policy Department of Almaty", according to which the replacement of an elevator that has exceeded the established service life is required. Since the start of operation, the elevator has worked for 42 years.

Before

After

In 2021, according to the Investment budget, a feasibility study and design estimates were developed:

– Development of a feasibility study for the modernization of Almaty CHPP-2 with minimization of environmental impact for the department of CHPP-2 of JSC "AlES" – completed. A positive expert opinion has been received;

– Reconstruction of the ash dump at CHPP-3. 4 turn. Development of design and estimate documentation – completed. A positive expert opinion has been received;

– "Major overhaul of the security perimeter with the installation of fences, video surveillance, outdoor lighting at the facilities of the HPP Cascade: HPP-6 Pressure Basin and Water Intake of the Kazachka River. Development of the WD (Working Draft)" – completed. A positive conclusion of the examination was received.