The press-tour is carried out on the objects of energy and heat supply in Almaty region.

ALMATY. The 6th of January. KAZINFORM /Berik Bekmurzaev/ - All power equipment repaired to 100%, repair costs amounted to 4.5 bln. tenge.The age of the "AlES" JSC energy sources are from 31 to 76 years. To maintain the current production level of energy sources repair campaign fully carried out in 2011 in accordance with the approved schedule.

In order to ensure trouble-free operation of the generating equipment, the necessary fuel reserves, chemicals and spare parts for the operational needs of the energy sources of "AlES" were created. Monthly coal reserves of 454.1 thousand tons and 43.4 thousand tonsof fuel oilhave been established.

“AlES”, JSC defined a number of primary strategic projects aimed at increasing capacity: commissioning of the boiler and the boiler unit №8 at CHP-2; two gas turbine units at CHP-1; construction of Kerbulak hydroelectric power station and others.

http://www.inform.kz/rus/article/2431146